Commons Redesign Will Finish in Fall 2014

Print More

By SARAH CUTLER

Correction appended

Despite facing budgetary problems in February, a redesign of the Ithaca Commons is on track for completion in fall 2014 after a break in construction over the winter, according to Project Manager Michael Kuo.

The $10-million redesign project — which will bring improved amenities and aesthetics to the Commons, along with repaired infrastructure — received bids that came in over its budget and required an additional $2 million in funding, which the Common Council has since granted, according to Kuo.

Still, Kuo said the project team has had to cut costs by eliminating certain elements of the new design, including a playground, fountain and two gateway arches at the entrances to the Commons.